Wind farm costs

This section contains information about wind farm costs (both as lifetime costs and a detailed cost breakdown) and about levelised cost of energy (LCOE).

Costs

Site definitions

We have calculated a set of costs for a floating offshore wind farm, based on the following site conditions and assumptions:

ParameterDataUnit
Year of FID2028
First operation date2030
Wind farm rating1000MW
Turbine rating15MW
Water depth at site100m
Annual mean wind speed at 100 m height10m/s
Distance from offshore substation to shore75km
Distance from shore to onshore substation10km
Distance from wind farm to construction port75km
Distance from wind farm to O&M port75km
Floating substructure material and typeSteel semi-submersible
Mooring system6 point mooring with drag embedment anchors
Floating substructure manufacturing locationAsia
Floating substructure assembly locationEurope
Offshore substation foundation typeFixed jacket foundation
Ground conditionsBenign, allowing a piled substructure for the substation and drag embedment anchors for the floating offshore wind turbines

Lifetime costs

The pie chart below shows the contribution of each major cost element to the total lifetime cost of a floating offshore wind farm based on the site conditions and assumptions in the above table.

 

Detailed cost breakdown

A more detailed breakdown of typical costs is presented in the table below.

  • All costs are real 2024 prices.
  • Figures presented are rounded, hence totals may not equate to the sum of the sub-terms.
  • There can be a range in prices of any element between projects, due to specific timing, local issues, exchange rates, competition and contracting conditions, so values stated should only be seen as indicative.
  • Prices for large components include delivery to nearest port, and supplier and warranty costs.
  • Developer costs (including internal project and construction management, insurance, typically spent contingency and overheads) are included in the highest-level boxes but are not itemised.
CategoryRounded costUnit
Development and project management155,000£/MW
Development and consenting services72,000£/MW
Environmental impact assessments11,000£/MW
Development activities and other consenting services62,000£/MW
Environmental surveys9,000£/MW
Animal surveys (benthic, fish, shellfish, mammals and birds)7,000£/MW
Onshore environmental surveys1,000£/MW
Human impact studies1,000£/MW
Resource and metocean assessment7,000£/MW
Structure4,000£/MW
Sensors3,000£/MW
Maintenance1,000£/MW
Geological and hydrographical surveys9,000£/MW
Geophysical surveys3,000£/MW
Geotechnical surveys5,000£/MW
Hydrographic surveys2,000£/MW
Engineering and consultancy9,000£/MW
Project management48,000£/MW
Wind turbine1,350,000£/MW
Nacelle834,000£/MW
Rotor360,000£/MW
Tower156,000£/MW
Balance of plant2,418,000£/MW
Dynamic array cable115,000£/MW
Export cable269,000£/MW
Cable accessories80,000£/MW
Interface30,000£/MW
Cable protection4,000£/MW
Buoyancy2,000£/MW
Connectors and joints43,000£/MW
Floating substructure1,313,000£/MW
Structure1,103,000£/MW
Secondary steel53,000£/MW
Systems92,000£/MW
Corrosion protection65,000£/MW
Mooring systems316,000£/MW
Anchor systems35,000£/MW
Mooring lines and chains174,000£/MW
Jewellery98,000£/MW
Topside connection6,000£/MW
Installation aids3,000£/MW
Offshore substation282,000£/MW
HVAC electrical system80,000£/MW
Auxiliary systems13,000£/MW
Topside structure123,000£/MW
Foundation65,000£/MW
Onshore substation44,000£/MW
Electrical system31,000£/MW
Buildings, access and security13,000£/MW
Installation and commissioning1,376,000£/MW
Inbound transport154,000£/MW
Mooring and anchoring pre-installation153,000£/MW
Floating substructure - turbine assembly72,000£/MW
Crane and lifting equipment34,000£/MW
Technician services11,000£/MW
Marshalling port22,000£/MW
Other5,000£/MW
Floating substructure - turbine installation114,000£/MW
Offshore cable installation171,000£/MW
Onshore export cable installation8,000£/MW
Offshore substation installation52,000£/MW
Onshore substation construction29,000£/MW
Offshore logistics13,000£/MW
Sea-based support6,000£/MW
Marine coordination2,000£/MW
Weather forecasting and metocean data1,000£/MW
Marine safety and rescue4,000£/MW
Contingency and insurance610,000£/MW
Operation, maintenance and service98,000£/MW/Year
Operations, maintenance and service port0£/MW/Year
Operations34,000£/MW/Year
Operations control centre1,000£/MW/Year
Training3,000£/MW/Year
Onshore logistics1,000£/MW/Year
Technical resource (onshore and off)7,000£/MW/Year
Admin and support staff (onshore)8,000£/MW/Year
Insurance14,000£/MW/Year
Offshore logistics7,000£/MW/Year
Maintenance and service57,000£/MW/Year
Turbine maintenance and service41,000£/MW/Year
Balance of plant maintenance and service15,000£/MW/Year
Statutory inspections1,000£/MW/Year
Decommissioning450,000£/MW
Floating hull - turbine decommissioning148,000£/MW
Mooring and anchoring decommissioning122,000£/MW
Cable decommissioning137,000£/MW
Substation decommissioning42,000£/MW

Levelised cost of energy

Purpose of LCOE

LCOE is defined as the revenue required (from whatever source) to earn a rate of return on investment equal to the discount rate (also referred to as the weighted average cost of capital (WACC) over the life of the wind farm. Tax and inflation are not modelled. In other words, it is the lifetime average cost for the energy produced.

LCOE is used to evaluate and compare the cost of electricity production from different technologies and at different locations. It is a good way to compare the cost of a unit of energy (say in pounds per megawatt hour of electricity (£/MWh)) produced. LCOE does not consider costs relating to balancing supply and demand.

Lower LCOE benefits the electricity consumer (and tax payers if any subsidy is paid to generators), so decreasing LCOE is a key focus for the offshore wind industry.

LCOE combines costs and energy production into one metric, rather than comparing cost and energy production separately. It is used by technology players and industry enablers, but typically not by project investors who may be more interested in internal rate of return (IRR) or net present value (NPV) of an investment, taking into account more company-specific features like tax.

In the UK, subsidy for offshore wind farms is currently provided through UK Government Contract for Difference (CfD) auctions. CfD bid price is the revenue ($/MWh) sought by the developer for a 15 year duration. Revenue after this will come from the open market. The bidder’s prediction of future market prices and its approach to risk and competition will determine how it sets its CfD bid price. The CfD bid price therefore is not equal to LCOE, though there is a relationship between the two. In different markets, the scope of supply of the project developer and the terms of the competition vary, meaning that there is a different relationship between CfD bid price and LCOE.

In Japan, subsidies for offshore wind farms are provided through Public Auction System for Offshore Renewable Energy, established under the Renewable Energy Sea Area Utilization Act (2019). Auctions are conducted by the Ministry of Economy, Trade and Industry (METI) and the Ministry of Land, Infrastructure, Transport and Tourism (MLIT). Developers bid by proposing a supply price (¥/kWh) for a fixed contract period, typically 20 years. After this period, revenue will be determined by market conditions. The bid price is influenced by the developer’s expectations of future electricity prices, risk management strategy, and competitive positioning. Therefore, the bid price is not necessarily equal to the levelised cost of electricity (LCOE), though there is a correlation between the two. The relationship between bid price and LCOE varies depending on market structure, project scope, and auction rules in different regions.

In South Korea, offshore wind subsidies are provided through the Renewable Portfolio Standard (RPS) and the Feed-in-Premium (FIP) scheme, managed by the Ministry of Trade, Industry, and Energy (MOTIE). Unlike competitive auctions in other markets, South Korea’s RPS requires large utilities to source a set percentage of electricity from renewables. Developers earn revenue through Renewable Energy Certificates (RECs) and electricity sales, with offshore wind projects benefiting from higher REC multipliers. Introduced in 2022, the FIP scheme offers a premium above the wholesale market price instead of a fixed tariff, allowing for market-driven pricing. Bid prices reflect forecasts of electricity prices, risk strategies, and competition rather than directly equating to the levelised cost of electricity (LCOE), though a correlation exists. South Korea is transitioning toward competitive bidding for offshore wind, with a roadmap outlining a two-stage evaluation process that considers both price and non-price factors. This shift may reshape the current RPS and FIP frameworks, impacting project economics and investment dynamics.

Definition of LCOE

The technical definition of LCOE is:

Where:

It Investment expenditure in year t
Mt Operation, maintenance and service expenditure in year t
Et Energy generation in years t
r Discount rate (or WACC), and
n Lifetime of the project in years.

Drivers of LCOE

LCOE reduction can come from reduced costs, increased energy production, or changes in financing and lifetime of the project. Reduced cost can result from process or technology changes during the manufacturing, installation or operations phase. Increased energy production may result from technology or by reducing lost energy via better operational processes. Reducing project risk is the main way to affect financing cost.

The chart below shows BVGA’s LCOE forecast for floating offshore wind from 2027 (when the next pre-commercial floating offshore wind farms in the UK are expected to be commissioned) to 2035. LCOE varies between individual projects but overall LCOE is continuing to reduce significantly over time. The band shows the variance in LCOE that could occur for floating offshore wind projects driven by different site conditions, support mechanisms and local requirements that all impact LCOE. The variance is expected to tighten over time as the industry standardises across different technologies, and their associated manufacturing, installation and maintenance processes. The cost breakdown shown below reflects the higher commodity prices and altered market dynamics experienced by the industry post-2020. While some level of reduction in future commodity prices is expected, it is unclear on the timing or magnitude of this.

Some of the key drivers of cost are:

Site conditions

In waters less than 70 m deep, the mooring of some floating substructure types becomes more expensive because of the dynamic response to waves in these shallower waters.

Easy ground conditions, such as dense sand with low gradients or homogeneous or stiff clay containing few or no boulders, offer cost benefits because a range of anchoring solutions can be used and there is high confidence of long-term mooring system stability. Difficult conditions can add to cost significantly by driving a need for alternative designs and installation methods, such as suction or piled anchors.

Wind and wave conditions, tidal ranges and tidal flows also impact LCOE. Higher mean wind speeds increase cost but have a net benefit for LCOE due to increased energy production. In Japan and South Korea, typhoon winds could drive design changes that add cost. Large tidal ranges can add to cost because turbines are required to keep a minimum clearance from sea level to blade tip at all times and so require more flexibility in the mooring system. Tides and waves make it harder to access turbines, especially for unplanned maintenance and repair activities in bad weather, adding cost and reducing energy production.

Likewise, projects further from shore take longer to access which adds cost and increases downtime, which reduces energy production. At about 60 km, it may be most cost effective to use a service operation vessel (SOV) spending weeks at sea, rather than crew transfer vessels (CTVs) travelling to and from port daily. Projects further from shore typically also have longer grid connections, adding to transmission CAPEX and OPEX.

Over time, there has been a move by governments from providing an agreed fixed-value market mechanism to supporting offshore wind to auctions where project developers bid a price for electricity they will generate. This change drives competition at project level which is passed down through the supply chain. Also, as the industry matures, what used to be highly differentiated areas of supply become commodities, driving further competition.

In some supply chain areas, such as turbine supply, the market is not big enough to have more than a handful of suppliers competing globally. This limits competition. In other areas, such as cables and foundations, transport costs are low enough to enable a geographically diverse supply base to bid for supply. In locations where ports have drafts suitable for floating substructure-turbine installation and can support the provision of O&M port services, distance to the wind farm is key which localises competition.

Vessel charter prices are a good example of the impact of pan-sector competition. Whether considering large floating vessels or common tugs, cyclic variations in regional wind and oil and gas activity can have a significant effect of price.

Supply chain evolution

Over time, the supply chain will mature, as it did in fixed offshore wind, with larger players taking on wider scopes and more risk. Wider scope within one supplier has enabled more cross-disciplinary collaboration to reduce cost. Also, larger volumes have facilitated investment in design, manufacturing and installation tooling suited to higher-volume process repetition. Large offshore wind farms may use 100 sets of identical (or similar) components, quite different from the more common practice in oil and gas of constructing one-offs.

Technology development

To date, the biggest driver over time of cost of energy reduction has been the development of new technology. The most visible sign of this has been the increase in turbine rating, increasing from 2 MW turbines 20 years ago to 15 MW turbines for projects reaching FID in 2028.

Larger turbines help drive down the per MW cost of floating substructures, installation and operation, whilst reaching higher into the wind field, so increasing energy production per MW installed. Larger turbines drive a need for technology development at a component level, as offshore wind turbines use the largest castings, bearings, generators and composite structures in series manufacture in any industry.

Technology development in floating substructure design and manufacture will have a major impact on LCOE. This cost element is specific to floating offshore wind and currently makes up a very large proportion of CAPEX. As the industry scales up and optimises floating substructures, significant cost reductions will happen, just as they have for cost components in fixed offshore wind. Innovations in foundation substructures, such as lighter, more optimised designs, will reduce the amount of steel and other materials needed, lowering material and fabrication costs. Integration between turbine and foundation design could also help reduce costs. As the industry scales up, economies of scale and streamlined supply chains will further drive down costs. Additionally, increased project experience, and improved installation technologies, will contribute to making floating offshore wind more affordable and commercially viable over time, although this is dependent on deployment rates.

Industry incorporation of digital, autonomous, artificial intelligence and other applicable technologies is also enabling significant cost reduction, especially through improved wind farm operation and control.

Time

Considering the supply chain and technical factors described above, LCOE is projected to reduce over time.

The chart below shows BVGA’s LCOE forecast for European floating offshore wind from 2027 (when the next pre-commercial floating offshore wind farms in the UK are expected to be commissioned) to 2035. We expect LCOE in the Asia Pacific region to follow a similar trend, although absolute values may change. LCOE varies between individual projects but overall LCOE is continuing to reduce significantly over time. The band shows the variance in LCOE that could occur for floating offshore wind projects driven by different site conditions, support mechanisms and local requirements that all impact LCOE. The variance is expected to tighten over time as the industry standardises across different technologies, and their associated manufacturing, installation and maintenance processes. The cost breakdown shown below reflects the higher commodity prices and altered market dynamics experienced by the industry post-2020. While some level of reduction in future commodity prices is expected, it is unclear on the timing or magnitude of this.

LCOE trend chart

While the LCOE of floating offshore wind is expected to decline significantly as the industry scales and technology matures, it is likely to remain higher than fixed-bottom offshore wind in most cases. Even as economies of scale and innovation reduce the LCOE for floating wind, the inherent technical challenges and material requirements will continue to make it more expensive than fixed-bottom projects. This is largely due to the added complexity of floating foundations, mooring systems, and dynamic cabling, as well as the need for specialised installation and maintenance strategies in deeper waters. Further, fixed and floating offshore wind have different deployment locations. Floating wind is designed to access deeper waters and more technically challenging sites that fixed-bottom technologies cannot reach. These locations often involve harsher metocean conditions, greater infrastructure demands, and more complex engineering requirements leading to higher costs.

Guide to a Floating Offshore Wind Farm